Manipal Journal of Science and Technology

Abstract

Nowadays distributed generations are connected to the distribution network. The proper installation of DG improves the technical and economic impact of the system. The optimal siting and sizing improves system reliability and improves the capacity of the system. This paper discusses the optimum location and calculation of PV with load growth in the 400V and the 11kV feeders were studied. The load growth is made at the feeder up to the actual losses in the system. The test is conducted at each percentage of the load growth.